Order
The part type indicates the type of part:
Revision number, Reference date
The Revision number field shows the revision of the part specified on the selected line. If revisions are not used in your company, this field is always set to revision number '000'. Initially, this field contains the revision that is valid on the date the line was added.
Use this field to specify how the part is to be obtained, or in other words, the origin of the part. Initially, the order code of the part determines the origin type. For example, the order code 'Purchase to order' is translated into the origin type 'Distributed origins', and the quantity is then entered in the Purchase field.
You can modify the origin type:
|
To include the production order of the semi-finished product in the production order of the production part for which it is required, choose 'Copy calculation and delete part'. The calculations relating to the production part and the semi-finished product will then be reduced to one level and therefore to one production order. Also the reference to the semi-finished product is removed from this calculation, as the part number of the semi-finished product is replaced by all elements of which the semi-finished product is composed. |
|
This setting has virtually the same effect as the 'Copy calculation and delete part' setting, where the calculations for the semi-finished product and the finished product of which it is a component are reduced to one level. However, this 'total calculation' no longer allows you to see which parts, operations, etcetera belong to the semi-finished product, and which belong to the finished product. To merge the underlying calculations into one calculation, while still being able to see the product the parts, operations, equipment and external operations belong to, choose 'Copy calculation and do not delete part (phantom)'. The calculation will then include a phantom line which shows the semi-finished product the underlying calculation components are intended for. All part lines, operation lines, equipment lines, and external operation lines referring to the semi-finished product will contain a reference to the phantom line. |
|
Use this setting to indicate that the part is supplied by the customer (who has ordered the finished product in which it will be included). |
|
If you choose this option, use the Stock, Purchase, and Production fields in the Distributed origins section to specify the origins of the part and the quantities obtained from those origins. |
Example
If the finished product of the production file is a cabinet, the cabinet shelves may be a component of the calculation. The origin type will then indicate the origin of these shelves:
If the part line contains a semi-finished product, you can copy the calculation of the semi-finished product to the line (phantom). Once you have done so, the Copied check box will be selected. If you cancel the calculation lines, this check box will be deselected.
The field can also be changed manually, but only if the order code is 'Copy calculation and do not delete part (phantom)'.
Operation
This field contains the first operation for which the part is required. It is important to fill in this field, as the part will then be included in the planning.
For part lines with a 'Production' origin, this date field is populated, during the Perform lead time planning process, with the end date of the supplying production file plus one day. The date therefore indicates when a semi-finished product will be available for use.
The calculation of the 'Date available' takes into account any waiting times. If a production file will be complete on October 27, and the 'Waiting time after' is one day, the Date available on the part line will be October 28.
The start date of an operation depends both on the end date of the previous operation, and on the availability date of the parts required. The latter of these dates will ultimately determine the start date.
Dimensions
This is the number of pieces of the part you need in order to make the finished product.
Note: When building the calculation, you should take into account the quantity that needs to be created for the production file (see the Quantity field on the General tab of the production file). For example, if the quantity ordered is '10 pieces', fill in the quantity required to produce ten parts.
Specify the length, width, and/or height per piece. Whether or not you can fill in one or more of these fields depends on the setting of the Unit code field on the General tab of the Parts form:
Unit code |
Can a length be filled in? |
Can a width be filled in? |
Can a height be filled in? |
Quantity |
No |
No |
No |
Quantity * Length |
Yes |
No |
No |
Quantity * Length * Width |
Yes |
Yes |
No |
Quantity * Length * Width * Height |
Yes |
Yes |
Yes |
The number in this field is calculated automatically by multiplying the quantity, the length, the width, and the height. The value of this informational field cannot be modified directly.
Note: If the Show costs including waste check box was selected from the Settings menu, the value in this field is including any waste. If the check box is not selected, the waste will not be taken into account.
The weight and surface of the parts can be displayed only if a weight/surface has been specified for the part on the General tab in the Parts module.
Note: If the Show costs including waste check box was selected from the Settings menu, the values in these fields are including any waste. If the check box is not selected, the waste will not be taken into account.
Distributed origins
If the origin type of this part is 'Distributed origins', fill in the quantities to be obtained from each of the origins in these fields. It is possible to enter a combination of origins, so you could have 10 units with a 'Stock' origin, 5 units with a 'Production' origin, and 25 units with a 'Purchase' origin.
If you enter a quantity in the Production field, you can choose to immediately create a production file for the parts to be produced.
Authorization
When you authorize a part line, you are indicating that the part line has been approved. Isah will then take into account that the part is needed on the required date. If, for example, the part must be purchased, it will appear on purchase requirements, so that it can be purchased in time.
Tip
If a purchase requirement was created for the part line, you can no longer save the line after you have canceled the authorization. To save any changes after all, do the following:
If a purchase order line was created for the part line, you can no longer cancel the authorization. To apply any changes after all, do the following:
This is the date on which the part is needed in the production process. This field is used, for example, to display the part on the purchase requirement when it needs to be purchased. The required date can be filled in different ways: