Use the Copy projects process to copy data from existing projects to new projects. Select the project or project component you want to copy the data to, open the Copy projects process, select the project or project component from which you want to copy the data, and then choose the data to be copied. There are a few points to consider:
The project (or project component) from which you will copy data must be of the same type as the project (or project component) you are copying the data to. In other words, you can only copy data from one project to another project, from one activity to another activity, etcetera.
If you choose to copy data that already exist in the new project, those existing data will not be overwritten.
When you open the Copy projects process from the Projects form, you can only copy data from one project to another project. If you start the process from the Project lines - planning form, you can copy data from all project types.