Start time in Production calculation for operations

The General tab of the Production calculation for operations form has a new Start time field.

Use the start time if you want to schedule multiple operations on one day. Enter the start of the operations in the Start time field, and specify the duration of the operation as the cycle time. The Start time field will be cleared if you run the Cancel planning process.

Note: The start time does not affect the planning logic in Isah, which uses days. The field is intended to allow you to specify the order of the operations during the day.