MRP: Check low-level code

Initially, Isah looks for the parts with the lowest low-level code (code 0). For all of these parts, the steps Create purchase requirements and production files, Copy calculation to production file and Perform lead time planning are performed.

The software then returns to the step Check low-level code, and the code is incremented by 1. This cycle is repeated until the lowest level (the highest number) has been reached and all parts have been calculated.