1185 Synchronize engineering/production - Part calculation

It is possible to also copy the part calculation during synchronization if an engineering BOM contains parts with a part calculation, or if the part linked to the engineering item has a part calculation. During each synchronization, the production structure is synchronized with the engineering structure; the part calculation is usually copied just once.

Instead of synchronizing all calculation components, you can also choose to copy only the parts and operations from the calculation. To retain the links between calculation lines, for example the links between parts and operations, you need to copy both types of calculation lines at the same time.

The prerequisite for copying calculation lines differs for linked parts and parts on the engineering BOM:

Fields

Use line numbers from part calculation (do not renumber production calculation)

Numbers of copied calculation lines to match phantom line

Also number invisible phantom lines