Use operation statuses to assign specific stages to operation lines. The use of operation statuses is not mandatory. You could use operation statuses such as: 'Waiting for material', 'Started', 'Waiting for quality check', 'Paused', or 'Complete'.
The plan type of an operation status indicates whether an operation with this status can be scheduled, and if so, how. You can choose from the following options:
No planning:
The operation will not be included in the Perform lead time planning process, and it is not possible to plan (or re-plan) the operation manually.
Planning allowed:
The operation will be included in the Perform lead time planning process, and it can be planned (or re-planned) manually.
Planning via processing only:
The operation will be included in the Perform lead time planning process, but it is not possible to plan (or re-plan) the operation manually.
Only manual planning:
The operation will not be included in the Perform lead time planning process, but it is possible to plan (or re-plan) the operation manually.