The operation filters under Default settings are default values that can be changed per terminal in SFC. To do this, create a new filter definition under Terminal-specific settings for every terminal that needs separate settings.
This setting determines the maximum number of operations shown in the Operations form. The number can't be zero; the default value is 20. There is no maximum setting, but the higher the number of operations you specify here, the more time it will take Shop Floor Control to load them.
Shop Floor Control will always show at least one operation that is not running. In some cases, this can result in a list that has more than the maximum quantity of operations. For instance, if you have set the maximum to 5, the setting Show operations in progress is active, and all 5 operations are running, SFC will show a sixth line that has not started yet.
If this setting is active, the Operations form will also show WIP operations (Work In Progress; operations that are started by one or more users). If it is not active, WIP operations will not be shown.
This setting determines the operations that will be shown in the Operation overview. The configured range will be checked against the status of the production order of the operation. If the status is not within this range, the operation will not be shown.
This setting determines the operations that will be shown in the Operation overview. The configured range will be checked against the status of the operation. If the status is not within this range, the operation will not be shown.
With this setting, you can rule out operations that are not eligible for work, based on the availability of the materials. You can set a minimum level of availability for all materials. If an operation does not meet this condition, it is not shown in SFC.
With this setting, you can rule out operations that are not eligible for work, based on the progress of the previous operations. You can set a minimum state for any previous operation. If an operation does not meet this condition, it is not shown in SFC.
This setting is used when operations are retrieved. The number of days in the future is specified by the value of this setting. If no number is supplied, all operations are retrieved.
Terminal-specific settings
If a specific terminal needs a set of operation filters different from the default values, create a filter definition for this terminal here. Users will then be able to select this filter definition on the terminal.
Click the plus to add a filter definition.
Add a description for the filter, for instance the location in your company. Adjust the various filters so they apply to this filter definition.