Click the Subsequent operations button on the Operations calculation form to link the operation lines of the standard part to each other, in order to define an operations sequence. This is relevant for the planning, amongst other things.
When specifying subsequent operations, you can:
Internal transport times and waiting times refer to the times in between two operations. This means that for the first operation and the last operation, the transport times must be entered differently. You can do so in two ways: