If you use line operations, use Split up line operations to make them visible in the Time registration records.
There are two ways of recording hours against a line operation:
Line operations and hour codes
If, for a particular line operation, you enter an hour code with which both labor and machine costs are posted, the hour line will be split up into an hour line for the line operation (with labor costs), and underlying lines for the various operations (with machine costs).
Only one hour line for labor costs can be created at any one time, because Isah is unable to process multiple hour lines for labor costs that have the same start and end time.
For the hour line for the line operation, Isah will look for an hour code with which only labor costs are posted, and for the hour lines for the different operations, Isah will look for an hour code with which only machine costs are posted. If you want to control which hour codes are used (for example, because you want to include them in reports), perform the steps below:
If, for a line operation, you enter an hour code with which only machine costs are posted, Isah will only create hour lines for all underlying operation lines. The line for the line operation will disappear, as it always relates to labor hours.