Example of scheduling based on infinite capacity

A production file with two operations must be scheduled. These operations take place consecutively.

Production file - to plan

The capacity and load of the capacity group for operation A will look like this:

Capacity group A

The capacity and load of the capacity group for operation B will look like this:

Capacity group B

Assumptions

Results

When planning based on infinite capacity, the plan time for the operations is matched against the capacity of the capacity group. Other production orders that have already been scheduled are not taken into account. Production file X will therefore be scheduled as follows:

The load of the capacity groups will be as follows:

Capacity group A with overload

Capacity group B with overload