Use the Change plan data process to change plan details as a batch. This could be useful if, for example, you want to change the planning type of production operations from 'Infinite capacity' to 'Finite capacity'.

With the exception of two fields, all fields that can be changed with this process can be found in the 'production calculation for operations' on the Planning tab. The other two fields (Status and Complete) are found in the 'production calculation for operations' on the General tab.

Fields

Selection, Selection criteria

Plan time

Minimum lead time

Fixed lead time

Planning basis

Planning type

To plan per day

Contiguous

Restriction

Priority

Status

Complete