The Run MRP process consists of the following steps:

Calculate part levels

 

 

Delete purchase requirements and production files

 

 

Check low-level code

Pijl naar boven en links

 

Create purchase requirements and production files

 

 

Copy calculations to production files

 

Perform lead time planning

 

Note: At the end of each cycle, the low-level code is incremented by 1. As soon as the last low-level code has completed the cycle, the process ends.