Use the Subsequent operations form to link the operation lines of the production file to each other and to define an operations sequence. This is relevant for the planning, amongst other things.
Internal transport times and waiting times refer to the times in between two operations. This means that for the first operation and the last operation, the transport times must be entered differently. You can do so in two ways:
Create the transport times and/or waiting times as separate operations. Using this method, you cannot use the default values for the next operation, however.
Create a dummy for the first and/or last operation, and specify the relevant transport times and/or waiting times.
To specify a name for a processed component, enter the name in this field. The field is used when shipping components for an external operation. If you have entered a name in the Component field for a component to be processed externally, you can specify the component to be sent on the Components to ship form.