The Operations form lists the operations that can be started and the operations that are currently in progress. The list is sorted by priority. You cannot change this sorting order; the order is set in the SFC configuration tool. Use filters to reduce the selection of the operations displayed.
The columns display more information about every operation:
If this icon is displayed in the Started column, the operation has started, or was started at some point and was then stopped, but has not yet been finalized. Finalized operations will be removed from the form immediately. |
|
If the In progress column is empty, the operation has not started, or was started and then stopped without being finalized. If the column contains this icon, a machine is working on the operation. If you see a photograph of an employee, then that employee is the person working on the operation. |
|
Quantity |
This is the number of items that is to be processed or produced based on the preliminary costing in Isah. You can record how many of these items you have finished by registering quantities. |
Material |
The color in the Material column indicates whether the materials required for the operation are available. The material with the lowest availability determines the color. Two color boxes in the Material column signify a cluster. The first box indicates the material availability for the line, and the second box shows the material availability for the cluster as a whole. |
Predecessors |
The color in the Predecessors column shows the status of the preceding operations. The operation with the lowest status determines the color of the column. If there are no previous operations, there is no color coding. |
Icons
This selection button is available if there is an underlying list from which you can choose values. Hold the button until a list appears, and then make your choice. |
|
Add an unplanned operation. |
|
Open the documents for the selected operation. |
|
Check the material availability for the selected operation. |
|
Check the equipment for the selected operation or production order. |
|
Create a new cluster and add the selected operation to it, or edit an existing cluster. |
|
Start the selected operation or the selected cluster. |