Planning based on labor or machine times

The planning process mainly consists of scheduling lead times of operations. Setup, adjustment, and operation times, which are used to calculate the lead time, can be specified for employees and for machines. Use the Based on field to specify whether you want the scheduling to take place based on labor times or machine times.

The Based on field is available in the capacity groups and in the operation calculation of production files. The value set for the capacity group is used whenever the capacity group is included in an operation calculation of a production file. The field value can still be modified here.

Planning using labor hours

Labor planning allows you to do the following:

Planning based on machine hours

If the planning is based on machine hours, the machine times from the operation line are used.

Note: Personnel schedules are not used for the Perform lead time planning process. Scheduling takes place based on the available capacity of the capacity group specified on the operation line.