Print the work order for the selected operation (the work order must have been created in Isah).
|
|
Issue materials for the selected operation.
|
|
Click this button to register quantities. You can also register quantities when you stop the operation. You will use the separate button mainly to register interim quantities, for example for an operation that takes multiple days.
|
|
Open the documents for the selected operation.
|
|
Click this button to stop an operation, or to stop and finalize an operation. In the window that displays, you can register quantities and report any failures. Then choose Stop this operation (if the operation will be continued later), or choose Stop and finalize this operation. If you choose the latter, the operation will be removed from the overview in SFC.
|
The Operations and Machine operations forms have a section at the bottom containing additional information about the selected operation (or machine operation). It consists of three boxes: Memo, Routing and Times.
Memo
This box contains the text from the Memo tab (in Isah) for the selected operation (or machine operation).
|
Display the memo field in full screen.
|
|
Increase the text size.
|
|
Decrease the text size.
|
If configured for your company, you can change the memo field. Tap the memo field to enable the Edit mode. You will now see a few additional buttons:
|
Save your changes
|
|
Undo the change
|
|
Redo the change (after undoing the change)
|
Routing
The Routing box shows the predecessors and the successors of the selected operation (or machine operation). Only one level of predecessors and one level of successors are displayed. SFC shows the progress by means of colors and a percentage:
- Green: Operation is complete
- Yellow: Operation has started and quantities have been registered
- Orange: Operation has started
- Red: Operation has not started.
Times
At the bottom of the Times box, you can see the current and expected times of the selected operation (or machine operation):
- The preliminary time is retrieved from Isah, and the actual time will start running when the operation is started in SFC. You can see the time on the Current operation form.
- If the actual time takes longer than expected, it will be marked with a red color.
- Two time fields may appear to the right of Actual costing. The first field shows the time expired during the current operation; the second field shows the total time.
The behavior of the Times box depends on the form on which it appears:
Form
|
Behavior of the Times box
|
|
If configured in the system settings, you can use the Times box to specify the type of operation you want to start. First choose 'Labor', 'Machine' or 'Labor+Machine'. You will now see the options available for your choice.
You can only select the combinations of 'Labor/machine/Labor+Machine' and 'Setup time/Adjustment time/Cycle time' that are defined on the Settings form of the SFC configuration tool. In the SFC configuration tool, an hour code has been defined for each valid combination. The combination you choose determines the hour code the operation is posted to in SFC.
|
|
You can see which hour code (combination of 'Labor/machine/Labor+Machine' and 'Setup time/Adjustment time/Cycle time') is active. You can change this hour code by selecting a new combination. When you select a new combination, it will start blinking. After two seconds, your choice will become permanent.
If the new hour code is of the type 'Machine', the current action is aborted for the employee, and a machine operation is started. SFC shows the Current machine operations form.
|
|
You can see which hour code (combination of 'Labor/machine/Labor+Machine' and 'Setup time/Adjustment time/Cycle time') is active. You can change this hour code by selecting a new combination. When you select a new combination, it will start blinking. After two seconds, your choice will become permanent.
If the new hour code type is not 'Machine', the current action for the machine is aborted, and an operation is started for the employee. The Current operation form is displayed.
Note: You can take over the machine operation only if you do not have any current operations yet. An employee can have only one current operation at a time.
|
|
The current action for the selected operation is displayed. This action cannot be changed on this form.
|